SECURED PROJECTS
  1. Western Power Distribution facilities in Nottingham and Hinckley incorporating around 1500 sq. metres of roof and 1000 sq. metres of cladding panels.  All WPD projects involve the systems are Tata Platinum Guarantee approved by certified installers like ourselves.

  2. Tewkesbury PCC is a new build medical facility and our element of works comprises around 600 sq. metres of rainscreen system.  The 2mm thick aluminium PPC coated planks are being supplied by Ash & lacy system along with the spacer system.  Work is due to start around May time.

  3. We have also secured another rainscreen project for refurbishment of Crowne Plaza hotel in Birmingham.  Around 300 sq. metres of 3mm aluminium cassette panels incorporating and Nvelope support system and insulation are being fixed back to existing brickwork.

  4. A new build project for Butlers Leap comprising around 1500 sq. metres of Kingspan RW composite roof and wall panels has been secured, with work due on site in April.

  5. Other projects picked up are a Sports hall building at Langley academy around 500 sq. metres of Kingspan Topdeck and composite panels on envelope.  We have also secured a small unit extension to a VW Listers dealership in Nuneaton along with some extension works for a medical centre in Birmingham, again all looking to start in the next quarter.
PROJECTS PROGRESS
  1. Work on the project at Q3 Langley academy is well on and the roof will be complete next month with the cladding works not far behind and all on time and programme.  The canopy entrance area is to be complete and Sports hall building following on shortly for completion in June.

  2. The project at Birch coppice has been finished on in January with the completion of the final element of works around 100 sq. metres of ceramic tile rainscreen system to the entrance fa├žade of the building.

  3. We have completed the projects at WMG at Warwick university, Battery Retail park in Selly Oak where we mechanically lifted the majority of cladding panels due to access restriction was done in a couple of days.   The projects for HL Thorne in Oldbury and Kilo internal partition cladding have been completed on time.